Week 7 – Lecture
Acknowledgement for contributions to Slide Content:
Dr Marco Antonio Amaral Feris

For this Lecture
Feedback on WBS and Procurement
Feedback on Cost Management (and Cashflow)
• Time Management
3
WBS and Procurement
Feedback

4
Cost Management and
Cash Flow

5
Time Management
Consider your constraints
• What activities – As Soon As Possible (to manage
emerging risks)
• What activities – As Late As Possible (eg cashflow)
• Operational (e.g. council limitations)
• Interactions – with Principle (site access)
• Interactions – with other contractors (competition for
access, safety)
• Other organisational projects (priorities)
Developing a Gantt Chart
• Start WBS tasks, then for each task;
• Decide how (resources)
• Estimate Time
• Determine dependencies
• Plot task on timeline
Generally completed by software you heard about in OPS939

line
Description
Duration
Start
Finish
Depend.
People
Resources

1.2.1
Survey
3 d
12/6/23
14/6/23
32
JSS P/L

1.2.2
Dig hole
2 d
15/6/23
16/6/23
33
Tom
Excav.

1.2.3
Insert Reo
3 d
17/6/23
19/6/23
34
Reo Crew

Developing a Gantt Chart
• Start WBS tasks, then for each task;
• Decide how (resources)
• Estimate Time
• Determine dependencies
• Plot task on timeline
Generally completed by software you heard about in OPS939

line
Description
Resources
12
13
14
15
16
17
18
19
20
21

1.2.1
Survey
Excav.

1.2.2
Dig hole

1.2.3
Insert Reo

9

WBS Task
Duration
Start Date
Responsible
% Complete

Off site Preparations
39
2/02/2021
Elect
74%

On site Preparations
15
13/03/2021
Elect
0%

Conduct Performance
6
28/03/2021
Elect
0%

Pack up and Clean up
11
3/04/2021
Elect
0%

Contract Obligations Achieved
0
14/04/2021
Elect
0%

Collect Marketing Material
10
14/04/2021
Elect
0%

Write Report
20
24/04/2021
Elect
0%

 

Days 20 40 60 80 100

Critical Path Work completed Milestone
Another Example
Consider Various Gantt Charts for PMP
• One for where the Contractor’s project(s) sits within the
Principal’s project
• One that shows the major deliverables/activities of your
project (scope of work)
• Note that for contractors, one of the major risk is usually
denied access.
Make sure you know how you are going to
manage this (eg contractual terms for handling variations).
• Principals should also consider how delays are managed
and avoided (where possible).

11

12

Expert academic writer and education specialist helping students in the UK, USA, and Australia achieve their best results.

Need help with your own assignment?

Our expert writers can help you apply everything you've just read — to your actual assignment.

Get Expert Help Now →
WeCreativez WhatsApp Support
Our customer support team is here to answer your questions. Ask us anything!
👋 Hi, how can I help?