Task 1: Networking A project consists of 9 activities, each with a specific duration stated in weeks. For example, Activity E takes 3 weeks to complete and can only be started after Activity C has been completed. Information on the 9 activities is outlined in the precedence table (Table 1) below. Construct the network diagram